June 23, 2020
Fourmile Canyon Drive paving delayed one day
Having trouble viewing this email? View it as a Web page.
A storm last Friday caused a delay at another job site for the paving subcontractor, so they will not be able to start work in Fourmile until Thursday morning. Paving will now take place Thursday, Friday, and Monday, instead of Wednesday through Friday. Lawrence construction will continue working in the canyon on other remaining project tasks, like ditches, shoulders, guardrails, retaining walls, landscaping, and signage, so continue to expect a lot of activity and travel delays of up-to 15-minutes.
Have a good day.
Andrew
Andrew Barth
Communications
Boulder County Public Works