Overview
Certain types of minor projects may be eligible for an expedited review called “Expedited Site Plan Review (ESPR)”. During this process, the same standards analyzed during a Site Plan Review (SPR) are reviewed in a shorter time frame (approximately 3-4 weeks).
An ESPR may be granted if the Community Planning & Permitting Department finds the proposal does not conflict with the standards listed in Article 4-806 of the Boulder County Land Use Code. However, the ESPR determination may include written terms and conditions. The project, even if expedited, is subject to all applicable building permit and building code requirements.
Article 4-802.D requires that adjacent property owners be notified of the request to expedite SPR and be given seven days to respond.
- Document: Expedited Site Plan Review Application Packet
- Document: Planning Review Fee Schedule
- Webpage: Expedited Site Plan Review Applications and Docket Information