Boulder County’s Building Publication B70 outlines the required documents and plan components for commercial building permit applications in unincorporated Boulder County. The printable checklist helps property owners, contractors, and design professionals prepare complete submittals for review. Additional building publications are available on the Building Applications and Forms homepage, and broader program information can be found on the Building Safety and Inspection division homepage or the Community Planning & Permitting department webpages.
Scam emails have been impersonating Boulder County Community Planning and Permitting staff. Learn how to spot a scam email.
Boulder County Building Publications
Commercial Plan Submittal Checklist - B70A
All construction drawings must be submitted in PDF format at the time of your online building permit application.
Visit the website Boulder County Permit Records and Online Application Submittals for the online application.
This document serves as a general reference and does not represent a complete set of requirements.
Commercial permit applications are applicable to buildings and structures that are other than one- and two-family dwellings and their accessory structures.
Boulder County issues a permit that includes all trades under one permit. Projects with multiple buildings require a complete submittal package for each building. Complete plans are required from each discipline. Deferred submittals are not allowed (except for fire protection systems) without prior approval of the Building Department. Refer to Boulder County Building Code Amendments for all currently adopted code editions and county amendments.
Please understand, quoting the code section(s) does not demonstrate compliance to the code on the plan set. Please show, or otherwise illustrate, how compliance is achieved with the proposed installation or proposed construction in detail.
Submittal Requirements
Applications and supporting documentation without the following information may not be accepted for review.
General Requirements
-
- Referenced Codes and Reference Standards, see the current Boulder County Building Code Amendments.
- Construction type
- Building Area (allowed and proposed)
- Building Height (allowed and proposed)
- Occupancy Group Classification
- Occupant Load(s)
- Fire Sprinkler system (partial or throughout or none)
- Fire Alarm system (partial or throughout or none)
-
- Note the type of materials, quantities or amount(s), use (open or closed system) and resulting occupancy classification.
- Indicate use, storage, and control areas with fire barrier ratings on plan.
Structural Requirements
Electrical Requirements
Mechanical Requirements
-
- List and specify each type of cooking appliance as defined by IMC section 202 and IMC chapter 5. Provide complete kitchen hood plans and show ventilation calculations, including make up air, for Type I or Type II kitchen hoods.
- All plans should coordinate with plan submittals made to the Boulder County Public Health Department-Food Safety Program.
Plumbing Requirements
Fuel Gas Requirements
Fuel gas, and liquid propane, installations shall comply with the Boulder County Building Code Amendments, IBC, International Fire Code (IFC), International Fuel Gas Code (IFGC), and referenced standards.
For new propane tank installations see Propane Tank Installation and Location Webpage (B23).
Energy Conservation Compliance Requirements
-
- Commercial Buildings-Prescriptive Compliance or Total Building Performance (IECC section C401.2 and subsections)
- Residential Buildings (Residential buildings that are not one- and two-family dwellings reviewed under the IRC) – Pathways include Prescriptive Compliance, Total Building Performance, or Energy Rating Index, etc. (IECC section R401)
Colorado Model Electric Ready and Solar Ready Code Compliance
-
- FUTURE ELECTRIC EQUIPMENT. Equipment or appliances necessary to support future all-electric space and water heating, cooking, or clothes drying.
- SOLAR-READY ZONE. A section or sections of the roof or building overhang designated and reserved for future installation of a solar photovoltaic system or solar thermal system. 40 percent of the roof area, 5 feet minimum width, oriented between 110 degrees and 270 degrees of true north.
- Solar-ready zone
- Structural design for roof loads, add 5 pounds per square foot
- Amperage capacity for each EV-ready space at main service panel
- Amperage capacity for each future electrical equipment at main service panel
Fire Code Requirements
This Publication is Printable