Background
The bridge that funnels Dry Creek #3 underneath Baseline Road east of Baseline Reservoir is in need of replacement. Public Works will replace the existing bridge with a larger structure that will increase drainage capacity. In addition, crews will replace the guardrail, restore the creek’s alignment, improve neighboring wetlands, and repave and restripe the project area.
Timeline
The project will take place in two phases. During phase one, in order to complete the bridge project, Xcel Energy will need to relocate a gas main and nearby overhead electrical wires. During phase two, Public Works and our contractor will complete the bridge installation.
- Phase I – Xcel utility relocation – Complete
- Phase II – Public Works bridge replacement- IN PROGRESS
Travel Impacts
A full closure of Baseline Road between Cherryvale Road and 75th Street is in place. Crews currently anticipate opening the road on Monday, Dec. 21. This project has been delayed due to conflicts with multiple underground utility resources. After removing the more than 70-year old bridge, an old gas line was discovered that needed to be removed by Xcel Energy before crews could proceed. In addition, crews discovered that the City of Lafayette’s waterline ran closer to the structure that was planned, which required a redesign of one end of the new culvert.
Travelers on east and westbound Baseline Road will be detoured to South Boulder Road or Arapahoe Road. See a map of the detour and project location.
Trailhead Closure
The City of Boulder’s Dry Creek Trailhead will also be closed during the project. Please do not access the trailhead until the project has been completed.
RTD Bus 225
All bus stops for RTD’s 225 bus route will be closed between 75th Street and Cherryvale Road. The 225 will be detoured to South Boulder Road.
Current Bridge Condition

New Culvert (rendering)

Project Contact
- Andrew Barth – Public Works Communications Manager – abarth@bouldercounty.gov or 303-441-1032

