Flood Recovery Roads Projects

Project Name/LocationDescription of Work
Flagstaff RoadRoadway repairs of washed out section, including the creation of a 200-foot bridge. Also included rock wall repairs and retaining wall construction. Learn more
Longmont Dam RoadTemporary repairs included the construction of a temporary road, roadside and stream bank stabilization and the clean-out of N. St. Vrain Creek
Fourmile Canyon DriveTemporary repairs of the roadway included asphalt paving of the patches and new striping. Road side/streambank stabilization. Culvert repairs.
James Canyon DriveTemporary repairs of the roadway included asphalt paving of the patches and new striping. Road side/streambank stabilization. Culvert repairs.
Lefthand Canyon DriveTemporary repairs of the roadway included asphalt paving of the patches and new striping. Road side/streambank stabilization. Culvert repairs.
Geer Canyon DriveTemporary repairs of the roadway included asphalt paving of the patches and new striping. Road side/streambank stabilization. Culvert repairs.
Lee Hill DriveNew retaining wall. Repaving of the roadway. Streambank stabilization.
Raymond/Riverside CR 103Roadway was temporarily reconstructed in late 2013/early 2014. Permanent repairs and paving was completed in the summer of 2014
Logan Mill RoadWashed out culvert was replaced with a temporary structure
Salina Junction/Wall St./Gold RunTemporary repairs to the roadway, streambank stabilization, culvert repairs
Pine Brook HillsNew retaining walls were built on Timber Lane, Pinebrook Road, and Bow Mountain Drive. Culverts were also repaired or replaced and the road was resurfaced
Wagonwheel Gap Road/Pinto RoadTemporary repairs to the roadway, new culvert installation, streambank work, culvert repairs
East County Line Road at the St. Vrain RiverCreation of a new 270-foot bridge and the reconstruction of several hundred feet of roadway that washed out. New drainage was also created. Watch a Video
Big Owl & Cabin Creek roadsPermanent repairs of the roadway. Culvert repairs.
Boston Ave. Bridge in LongmontBridge and multi-use path repairs
LoBo Trail at Left Hand Creek/95th StreetMulti-use path repairs and landscaping
Topaz DriveTemporary repairs to the roadway and culverts
Valmont Road at South Boulder CreekRoadway and bridge repairs
6700 Valmont RoadTemporary roadway repairs and roadside stabilization
N. 61st & N. 63rd StreetsTemporary road and culvert repairs
Nimbus RoadRoadway repairs
Monarch RoadTemporary roadway and culvert repairs
Upper Flagstaff RoadNew retaining wall and roadway repairs
83rd St. at the Little Thompson RiverTemporary culvert installation
County Road 69Roadway repairs/repaving
Hygiene RoadRoadway and culvert repairs
95th StreetRoadway repairs and shoulder stabilization
Magnolia RoadRoadway repairs
Lickskillet RoadTemporary culvert and roadway repairs
Linden DriveRoadway and culvert repairs
Neva Road Roadway and culvert repairs